A few other things related to the bridges

A recent display ad in the Daily Sun stated that the Village of Chitty Chatty is only 4 miles from Brownwood. They left out the part that is if one uses 44. As inferred above, golf carts will have a much longer distance to travel.

Up near Water Lily, a 2nd larger crane has been moved to the bridge site on the north side of the turnpike, making it a total of 3 cranes available for the project. More importantly, a porta potty has made an appearance at the jobsite on the south side.

A few theories about the seemingly slower progress at Water Lily bridge location:

1. With the promotion of the homes and facilities at Chitty Chatty and Bradford, The Villages management team may be somewhat concerned about the other south of 44 residents who've waited a long time for connectivity. They've been waiting a long time for the promised connectivity. he newer residents of Chitty Chatty and Bradford will get their connection rather quickly. The recent activity near Water Lily might just be a pacifier to ward off the complaints.

2. Perhaps there are limited numbers of crews and equipment to make the Water Lily bridge happen. Waiting for the completion of the Chitty Chatty bridge over 44, then moving the crews to the turnpike bridge location.

Not helping anything is the COVID-19 matter, slowing the sale of homes. I've heard that the current inventory of new homes is around 2000 right now.

I don't have any inside information. All speculation on my part.

Mike
Village of Marsh Bend