I thought you had two or three months after putting $$ down on a lot, until you had to do design and begin construction. Can anyone confirm the time frame?
You have four months to start design after securing the lot. Construction usually starts within a few weeks after that. Our lot was secured in March 2020, design completed June 29, construction started Aug. 6, & home closing was Nov. 24.