As of Jan. 25, the site work of the First Responders Recreation Center is 80% complete, and the main building’s construction is 67% complete. The overall completion of the project is 76%. While the new recreation center was being built, the Recreation Department asked Villagers to contribute any first responders memorabilia that they might have.