Originally Posted by asianthree
ARC meets weekly, you can watch for agenda online, when a new village open they have hundreds of applications within Weeks of closing.
It’s our fourth new village, happens with each new village released, for about the first 4 months. Depending on how many newly released villages are selling homes (today more than in years past. The agenda fills quickly.
As I stated ours was among 146 homes just in our new neighborhood, plus add in the 3 other new villages, and preowned. Meeting only holds so many new business slots, and room for old business first.
Since we have been at this for awhile we didn’t make any exterior changes for 8 months, our ARC approval and permit were filed first week of September. Approval for pool, was end of October. Equipment arrived the day after approval. Our landscaping wasn’t filed until January, which was at the same time new release of 2 villages.
In 2007 agenda in a week, 2010 about 1.5 weeks. By 2020 month in not out of question, but multiple villages are released today then when we first arrived when one village was closing out, before next one released
|
That makes sense, I think I'm in district 14 so maybe or applications have slowed down a little making the 2 1/2 week turn around possible. The first application I put in was about Jan 1 and was about the same turnaround as I recall so maybe we've been slow send then?