Quote:
Originally Posted by Papa_lecki
I would guess the following timeline
3 months to figure out what you want to do (size, where, closet, etc)
2-3 months to pick your contractor
3 months for approvals
4 to 6 months construction
Is $250 to 300 a square foot a good number?
So 75,000 to 100,000
|
Thanks - very helpful! The first one will be quick - I designed my current home and have already laid out which floor plans have which potential and sketched out ideas. The picking the contractor I could at least start researching ahead. So likely the 9-12 month range sounds like.
75-100k is in my good zone - I’m guessing less if no bathroom. That puts it in the might-be-an-option category - thanks!