You will probably find that the time to build your house (from ground breaking to completion) and the time to close on it are significantly different. Our street was recently completed and it was amazing how fast they could put up a house (I'm guessing about 45 days). However, the time that they give you for closing is usually around 3 months or a bit more (we signed our contract on approx. 7/22 and closed on 10/31.) It took them several weeks before they actually broke ground (probably getting permits, etc. in place) and they were finished with the house in early October.