Cool Just Received .... CR101 Tunnel Update

The Latest Information:

Multi Modal Path Tunnel under CR 101
During a routine inspection of the multi-modal paths, District Property Management staff noticed cement pieces on the floor of the tunnel under CR101. Upon further investigation they found the cement had fallen from the tunnel. After cleaning the area of loose cement, they left and came back later to find additional cement had broken loose. At this time they requested our consulting engineer to look at the tunnel and determine what action would be necessary.

After examining the tunnel, it was suggested out of an abundance of caution that it be closed until further review could take place. The manufacturer was contacted, a structural engineer sent to The Villages and a decision was made to have core testing conducted on portions of the tunnel structure.

The testing is scheduled for Thursday, February 10th, and it will take approximately three weeks for the testing results to be completed.

At this point, out of continued concern for the safety and well being of residents, the tunnel will remain closed.

Any questions may be directed to Janet Tutt, District Manager, janet.tutt@districtgov.org or 753-4508.

Thank you for your patience and understanding regarding this unanticipated maintenance issue.