Old 09-05-2013, 11:47 AM
Bryan's Avatar
Bryan Bryan is offline
Veteran member
Join Date: Dec 2008
Location: Village of Alhambra
Posts: 832
Thanks: 0
Thanked 3 Times in 3 Posts
Send a message via MSN to Bryan
Default

There is no iron clad rule. This is an item that you negotiate with the contractor. They, of course, want as much as possible as soon as possible while you would prefer to pay as little as possible for as long as possible. A couple of finer points though - advance payment should be none or nearly so. Chose "milestone" payments that make sense to you and that you can easily check (i.e. slab poured, roof joists in place, etc.). Make the contract include a start and completion date. Final payment AFTER completion should be no less that 25% of total contract. Do a good final inspection, make sure you have all necessary paperwork in your hand (Building Permit, Certificate of Occupancy, ARC approval, etc), make sure all subs have been paid or you have a Release of Lien form from the general contractor, make sure all items on your 'punch list' are done, make sure work site is cleaned up and trash hauled away, and when you are completely happy, make that final payment to the contractor.