The First Responder Recreation Center is approximately 89% complete. The support buildings are approximately 95% complete, and the Putt & Play course and lawn bowling is approximately 98% complete. The total general construction project is approximately 94% complete. The general contractor is expected to complete this month. District work (furniture, fixtures, equipment, facility take over