How long to build a house in TV
I think my salesman said you had to start building on the lot 3 or 4 months after you purchase it. Does that sound correct?
Also what is the standard build time from signing contract to closing (not accounting for weather delays etc)? Thanks Ken |
As of now there is quite a backlog, designer meetings are booked out to October and then 3 to 4 months for the build so you're looking at February 2020 completion. Two of our friends just bought lots and that is the schedule they were given.
|
Time to build isn't the issue because you can't know when the Villages will start building your house, and your home and many others are built at the same time. But, when you sign the contract to build your home, the contract will include a closing date. The Villages has a reputation for never missing a closing date.
|
3 months
|
Back in 2013, it was you had to start building in 6 (six) months after purchasing a lot, and the completion was 3 months or less, ours took 80 days. You should be able to confirm the current requirements with a call to any of the sales offices.
|
Quote:
|
Quote:
|
Quote:
|
Quote:
|
Quote:
|
I bought a lot in Monarch Grove last week but can't get into the design center until late Sept.
Just noticed that area is no longer showing in the map portion of the Villages App, so maybe pulling it off the table until they catch up? |
Anyone know what the Design Center process is like?.
|
I don't know how long the design phase, etc. takes but I have watched homes go up. From the time the first workers show up on the lot to finish is about 57 days. The houses are all built on a tight schedule and if a subcontractor does not meet the schedule they are replaced.
|
Quote:
|
They sold 82 lots last month, usual amount is 20.
|
Holy smokes! Sales have really heated up!
|
Time to think about purchasing? Prices might increase soon
|
Quote:
Not sure if that is right..................normal numbers are selling 300 homes per month. |
I took a ride to Cattail and found a whole bunch of homes being built on the new golf course that should be opening soon, Last week I only saw the front of one home. Several of them are already sold as they have the buyers first names written on the window they are getting very close to 301, amazing what is going on.
|
The actual time to build a home here is about 4 days according to my observation
|
All times are GMT -5. The time now is 01:22 AM. |
Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2025, vBulletin Solutions Inc.
Search Engine Optimisation provided by
DragonByte SEO v2.0.32 (Pro) -
vBulletin Mods & Addons Copyright © 2025 DragonByte Technologies Ltd.