Talk of The Villages Florida

Talk of The Villages Florida (https://www.talkofthevillages.com/forums/)
-   The Villages, Florida, General Discussion (https://www.talkofthevillages.com/forums/villages-florida-general-discussion-73/)
-   -   Current time frame…. Design date till Closing (https://www.talkofthevillages.com/forums/villages-florida-general-discussion-73/current-time-frame-design-date-till-closing-320988/)

Woodbear 06-25-2021 10:40 PM

Current time frame…. Design date till Closing
 
For those newer to The Villages, can you share the length of time it has taken to build your house. I have heard from one person it is currently around 5 months from design sign off to closing.

Is this a typical timeframe?

Philbot 06-26-2021 06:31 AM

We reserved a lot in January, had the design meeting in mid-March, and will close the end of July.

Altavia 06-26-2021 07:04 AM

The process starts after the design meeting and historically has been three Months.. They do not miss a closing date.

Kenswing 06-26-2021 07:05 AM

Quote:

Originally Posted by Woodbear (Post 1965091)
For those newer to The Villages, can you share the length of time it has taken to build your house. I have heard from one person it is currently around 5 months from design sign off to closing.

Is this a typical timeframe?

Four months as a general rule. A bit longer if you're having a pool installed.

Kenswing 06-26-2021 07:11 AM

Quote:

Originally Posted by Robbie0723 (Post 1965166)
The process starts after the design meeting and historically has been three Months.. They do not miss a closing date.

Unfortunately that is no longer true. Because of material shortages some homes in St. Catherine were pushed out by up to 5 weeks. Windows were an issue for a few months. Our house was actually built without the master bedroom window being installed. It finally showed up about two weeks prior to closing. Many houses (ours included) closed without all the appliances being installed. When we moved in (late April) all we had was the cooktop. Three weeks ago we finally got our oven/microwave and two weeks ago we got our range hood. Thankfully we had a summer kitchen installed so we had the grill to cook on.

Dani & Bill 06-26-2021 08:45 AM

Quote:

Originally Posted by Woodbear (Post 1965091)
For those newer to The Villages, can you share the length of time it has taken to build your house. I have heard from one person it is currently around 5 months from design sign off to closing.

Is this a typical timeframe?

We signed the contract to build a Woodside model with a pool in Hawkins on April 30. They said construction would begin June 18, and it did. Scheduled occupancy is Oct 14, without appliances. We were told the pool would add a month.

Woodbear 06-26-2021 11:31 AM

Quote:

Originally Posted by Kenswing (Post 1965175)
Unfortunately that is no longer true. Because of material shortages some homes in St. Catherine were pushed out by up to 5 weeks. Windows were an issue for a few months. Our house was actually built without the master bedroom window being installed. It finally showed up about two weeks prior to closing. Many houses (ours included) closed without all the appliances being installed. When we moved in (late April) all we had was the cooktop. Three weeks ago we finally got our oven/microwave and two weeks ago we got our range hood. Thankfully we had a summer kitchen installed so we had the grill to cook on.

I notice a lot of new build homes listed for sale are missing appliances.

waterlily 06-26-2021 12:14 PM

Closed in Bradford recently. The Villages delayed closing twice. About two weeks late. They just cant keep up. Had to sign a contract that I would not pull a permit for 90 days as Sumter County is also behind. These are intersting times!

Woodbear 06-26-2021 08:01 PM

Quote:

Originally Posted by waterlily (Post 1965321)
Closed in Bradford recently. The Villages delayed closing twice. About two weeks late. They just cant keep up. Had to sign a contract that I would not pull a permit for 90 days as Sumter County is also behind. These are intersting times!

Pull a permit for additional work on the home post closing?

Dotneko 06-27-2021 04:56 AM

19 weeks for us with no pool.
Design mid jan, ground break feb 4, close may 24.

Rosebud1949 06-27-2021 05:00 AM

Quote:

Originally Posted by Woodbear (Post 1965091)
For those newer to The Villages, can you share the length of time it has taken to build your house. I have heard from one person it is currently around 5 months from design sign off to closing.

Is this a typical timeframe?

Hopefully taking 5 months will make sure they get it right the fist time. not have months of "repairs" and corrections done as some folk I know.

richs631 06-27-2021 06:24 AM

It’s about 6 months from start to finish but rest assured that your house will be ready on the date it is promised

Altavia 06-27-2021 06:28 AM

Quote:

Originally Posted by Rosebud1949 (Post 1965487)
Hopefully taking 5 months will make sure they get it right the fist time. not have months of "repairs" and corrections done as some folk I know.

Really? Took less than 5 days for the list of minor items in my case?

Hiltongrizz11 06-27-2021 06:40 AM

All I know is that all you people chime in who had your houses built a year or more ago but are not count on your experience being the same now for new people.

Times now or nothing like they were before any other time. I double what they tell you.

Conniehar 06-27-2021 06:41 AM

3.5 months with pool - we signed the contract in February. They have changed the build time significantly because of demand and need for workers.

dewilson58 06-27-2021 06:47 AM

Quote:

Originally Posted by Hiltongrizz11 (Post 1965551)
All I know is that all you people chime in who had your houses built a year or more ago but are not count on your experience being the same now for new people. Times now or nothing like they were before any other time. I double what they tell you.

One Chimer stated June to October.

Another Chimer stated March to July.

Seem current to me.

jimbo2012 06-27-2021 06:51 AM

As of last week design completion, soonest was Dec 10th

Maryanne Hasley 06-27-2021 07:05 AM

Design Date Till Closing
 
We just had our design week with our final signing last Friday on June 18. We have a final build date of December 9, 2021. Due to building material shortages and delays, there is also a possible three month extension written into the contract, specifically to cover material shortage. We were told they have only had to make use of this extension twice.

Dgodin 06-27-2021 07:12 AM

Quote:

Originally Posted by Woodbear (Post 1965091)
For those newer to The Villages, can you share the length of time it has taken to build your house. I have heard from one person it is currently around 5 months from design sign off to closing.

Is this a typical timeframe?

Street of dreams in February, build start in April, closing in June.
The Villages builder
Was told permitting takes 30 days or more.
Outside builders seem to need more time.

irish2468 06-27-2021 08:57 AM

Quote:

Originally Posted by Woodbear (Post 1965091)
For those newer to The Villages, can you share the length of time it has taken to build your house. I have heard from one person it is currently around 5 months from design sign off to closing.

Is this a typical timeframe?

depending on what model and site, 3-6 months..and if you're adding a pool at the time of the build 9 months...that's the real story.

nick demis 06-27-2021 09:46 AM

3 - 5 weeks after signing they break ground. With a few exceptions, 3-1/2 to 4 months after breaking ground will be the closing.

nick demis 06-27-2021 09:51 AM

Quote:

Originally Posted by irish2468 (Post 1965644)
depending on what model and site, 3-6 months..and if you're adding a pool at the time of the build 9 months...that's the real story.

We just built in St Catherine and no one we know, regardless of design (about 50 other people that built) did it take anywhere near 9 months including those that have pools. There was a delay from the average of 3-1/2 months this past winter when they were having a problem with the window vendor that was causing a 3-5 week delay.... that's the real story from someone that has recently gone through it.

rrb48310 06-27-2021 11:25 AM

Us too
 
Quote:

Originally Posted by Maryanne Hasley (Post 1965575)
We just had our design week with our final signing last Friday on June 18. We have a final build date of December 9, 2021. Due to building material shortages and delays, there is also a possible three month extension written into the contract, specifically to cover material shortage. We were told they have only had to make use of this extension twice.

We also signed Friday June 18, closing December 15th with a pool. Don’t recall “three month extension” but did have a clause for a 30 day notice to extend closing date without any reimbursement from The Villages.

rferg40 06-27-2021 01:01 PM

Timeline
 
Design meeting was late April. Down payment delivered May 5. Closing set for Oct 12.

hughessah 06-27-2021 01:38 PM

Design completed and contract signed 6/11. Scheduled to break ground 8/9 and close 11/30 with no pool. Contract allows for unlimited delays due to covid 19, otherwise they would pay for accommodations and storage.

callalily 06-27-2021 02:04 PM

I just bought a spec home. About 3-4 weeks ago, I enquired about building on a lot and I was told the earliest design appointments were in October and that closing would be May, 2022.

waterlily 06-27-2021 03:25 PM

Quote:

Originally Posted by Woodbear (Post 1965444)
Pull a permit for additional work on the home post closing?

Correct.

Normal 06-27-2021 05:49 PM

We had our design appointments finish up this past Monday. Construction starts the last week of August and closing is December 14th.

Holly Richardson 06-27-2021 08:35 PM

Quote:

Originally Posted by Woodbear (Post 1965091)
For those newer to The Villages, can you share the length of time it has taken to build your house. I have heard from one person it is currently around 5 months from design sign off to closing.

Is this a typical timeframe?

We finished our design in February and just closed 6/22. It was about 4.5 months. They don’t start the build right after you sign and make payment. I think it was about 2 weeks. The building goes so quickly it’s amazing. They build a great house.

Woodbear 06-28-2021 01:23 AM

Quote:

Originally Posted by irish2468 (Post 1965644)
depending on what model and site, 3-6 months..and if you're adding a pool at the time of the build 9 months...that's the real story.

Mossy Oak model & no pool for us


All times are GMT -5. The time now is 05:26 AM.

Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2025, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO v2.0.32 (Pro) - vBulletin Mods & Addons Copyright © 2025 DragonByte Technologies Ltd.