Quote:
Originally Posted by asianthree View Post
Our pool is being installed by Fiesta Pools.start day 10/19.

Pool hole dug and dirt removed day, one.
Steel shell (rebar, not a roll, each bar placed separately, 10/21&10/22.
first inspection 10/24.
Concrete shell scheduled next week.
Week 3 concrete shell completed, along with plumbing.
Footings and tile this week.


We are farther along than other pools that have had active site for 30 days.

Difference is Fiesta family owned over 50 years, has their own guys, for pool, employees average 20 years and more with them.
Our pool was done in 11 weeks, very satisfied. Wiseman pools