Shimpy 07-15-2011 11:40 AM

Quote:

Originally Posted by mulligan (Post 371105)
Generally, there are 2 choices in reinforcement of building slabs in Florida. Steel mesh, usually 8x8 squares of welded #10 wire, with added 1/2 or 5/8 steel bar at the perimeter, or perimeter bars with fiberglass in the mix (sometimes called fibercrete). Both can be engineered to provide correct support and finished surface. This is really an oversimplification, but the general idea applies.

Thanks Mulligan, that answer my question. I knew the codes here were different than S Fla. due to different conditions, but that explains concrete to my satisfaction.

batman911 07-15-2011 12:30 PM

I worked in construction during the Summers when I was still in school. I remember that someone always sampled the concrete coming out of the truck when we poured a slab or any concrete structure. There are different grades of concrete (rated in pounds of pressure (PSI)) that are used according to the architects specifications. I believe it may have been the architectual firm that was sampling the concrete.

rubicon 07-15-2011 02:55 PM

Quote:

Originally Posted by mulligan (Post 371105)
Generally, there are 2 choices in reinforcement of building slabs in Florida. Steel mesh, usually 8x8 squares of welded #10 wire, with added 1/2 or 5/8 steel bar at the perimeter, or perimeter bars with fiberglass in the mix (sometimes called fibercrete). Both can be engineered to provide correct support and finished surface. This is really an oversimplification, but the general idea applies.

Do you know if The Villages builders are using either one of these reinforcement methods or none ? Also I noticed that builders pour the slab and immediately begin building on it. Does the concrete need time to cure and dry? If so for how long?

Shimpy 07-15-2011 04:18 PM

Quote:

Originally Posted by mulligan (Post 371105)
Generally, there are 2 choices in reinforcement of building slabs in Florida. Steel mesh, usually 8x8 squares of welded #10 wire, with added 1/2 or 5/8 steel bar at the perimeter, or perimeter bars with fiberglass in the mix (sometimes called fibercrete). Both can be engineered to provide correct support and finished surface. This is really an oversimplification, but the general idea applies.

I just took a close look and did see re-bar in the footer.

batman911 07-16-2011 01:41 PM

Rubicon,

Concrete setting times:

http://powerblanket.com/2008/01/31/t...-setting-time/

and you can add accellerators to speed up the set time:

http://www.fhwa.dot.gov/infrastructu...p/acclerat.htm


All times are GMT -5. The time now is 11:33 PM.

Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2025, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO v2.0.32 (Pro) - vBulletin Mods & Addons Copyright © 2025 DragonByte Technologies Ltd.