We are soon to be residents of TV and can hardly wait!! We have a closing date but are trying to get a construction schedule for the building process. Are these available and how can one be obtained? Just want to be able to see a few things as they are being done and must schedule flights to get in to check out. Overall the construction looks to be on the better side.

Also wanted to know what the max speed is on the golf cart paths?

She has another question, has anyone used the relocation services? What have been the experiences?

We are building in the Altamonte neighbor hood in St Charles.
  #2  
Old 03-10-2010, 11:15 PM
graciegirl's Avatar
graciegirl graciegirl is offline
Sage
Join Date: Mar 2008
Posts: 40,170
Thanks: 5,009
Thanked 5,783 Times in 2,004 Posts
Send a message via AIM to graciegirl
Default

Although I have not built, I have heard that the closing date is absolutely dependable. EVERYTHING here runs like clockwork. I know you will be pleased.

Welcome to you and your wife. You have made the right decision.
  #3  
Old 03-11-2010, 05:53 AM
redwitch's Avatar
redwitch redwitch is offline
Sage
Join Date: Oct 2007
Posts: 9,094
Thanks: 3
Thanked 80 Times in 37 Posts
Send a message via Yahoo to redwitch
Default

I'm sure you could get a building schedule but all dates would be tentative -- something scheduled for the 21st might not happen until the 23rd because of rain and high winds. They really do get it done in 30 days, but can't always promise to do something on the day scheduled even though they try.

Technically, the maximum speed on golf cart paths (or anywhere else unless you have a street legal cart and are on the street) is 19.9 mph. Sadly, most carts exceed this speed everywhere.

I know of one couple of that was very happy with the relocation service; another that was extremely unhappy.

You're moving into a lovely neighborhood. Good luck and welcome!
__________________
Army/embassy brat - traveled too much to mention
Moved here from SF Bay Area (East Bay)

"There are only two ways to live your life: One is as though nothing is a miracle; the other is as though everything is a miracle." Albert Einstein
  #4  
Old 03-11-2010, 10:35 AM
Bosoxfan
Guest
Posts: n/a
Default

Hi & Welcome!!
I don't know about a formal schedule but my real estate agent(Chris Hallmark) sent us pictures of progress weekly.We did everything long distance and were very pleased with Chris in the way he kept us informed.Good luck & once again welcome!!
  #5  
Old 03-11-2010, 11:37 AM
elevatorman elevatorman is offline
Gold member
Join Date: Oct 2008
Location: The Village Duval
Posts: 1,034
Thanks: 43
Thanked 201 Times in 104 Posts
Default

We had a home go up next door and it was fast. It was a frame home. The slab prep. took a day, then a day of nothing. Next day the slab was poured and finished, then another day of nothing. Then the framers showed up at 6 am and at about 4 the entire house was up with plywood on the roof. Shingles the next day and within 2 weeks the major work was done.

There was another home down the street that a week was spent on the framing that the next door did in a day. I think any schedule would be one with deadlines. In other words we will have this phase done in 2 weeks, we will have this done in 3 weeks. Also much of the work is subed out. So the subs may work on weekends or into the evening. I saw workers putting cabinets in at 10 in the evening.

TV uses 4 or 5 different builders each works at a different pace. The best thing for you to do is find out which builder is working on your house. and contact them directly. Ask your agent to get this info. or if you come down after your home starts go to the site and talk to the workers. Everything happens fast.
  #6  
Old 03-11-2010, 01:08 PM
skip0358's Avatar
skip0358 skip0358 is offline
Soaring Eagle member
Join Date: Jul 2007
Location: The Villages Florida
Posts: 2,290
Thanks: 89
Thanked 325 Times in 110 Posts
Default Updates

When ours was being built the salesperson sent us weekly picture updates of the house. we kep't them for an album. I took pictures for someone moving in down the street from us. You can probably get one of your neighbors to do the same. Our building started within a week of signing the papers and was done at leat 1 1/2 weeks before closing.
__________________
Patchogue, NY; Village of Bonita Sept.09
  #7  
Old 03-11-2010, 01:35 PM
kb8tpw's Avatar
kb8tpw kb8tpw is offline
Senior Member
Join Date: Sep 2008
Location: St Charles
Posts: 468
Thanks: 0
Thanked 2 Times in 2 Posts
Default

Skip0358's schedule sounds about like ours. We close on the 22nd and Mary Edwards confirmed yesterday afternoon that our grass was being put down. They started a few days after purchase agreement was finalized. Her very frequent photo coverage since they started has been absolutely great. Here's a shout out to Ed and Mary Edwards and we plan to use their home watch service for a few months as well. She has gone over and above anything you could imagine and you'll see Mary around TOTV for sure. Ray and Barbara..
  #8  
Old 03-12-2010, 12:00 AM
soonfl soonfl is offline
Member
Join Date: Jun 2009
Posts: 83
Thanks: 0
Thanked 0 Times in 0 Posts
Default Fyi

FYI it would seem that your unit is in Pennecamp no ST Charles. Welcome


VILLAGE OF PENNECAMP (District 8)
UNIT 158
UNIT 165
UNIT 166
UNIT 167
UNIT 168
UNIT 169
ALTAMONTE VILLAS
AMBERJACK VILLAS
AZALEA VILLAS
BOXWOOD VILLAS
JACARANDA VILLAS
KINGFISHER VILLAS
MANGROVE VILLAS
Closed Thread


You are viewing a new design of the TOTV site. Click here to revert to the old version.

All times are GMT -5. The time now is 05:43 AM.