How is the Water Lily bridge progressing?

Closed Thread
Thread Tools
  #1  
Old 12-24-2020, 11:05 AM
kpd3062's Avatar
kpd3062 kpd3062 is offline
Senior Member
Join Date: Aug 2017
Location: Texas
Posts: 123
Thanks: 410
Thanked 39 Times in 21 Posts
Default How is the Water Lily bridge progressing?

I have been gone for the last month and a half. I just read about Brownwood bridge and Meggison road opening. Have any of you been by Water Lily recently? Thanks
  #2  
Old 12-24-2020, 11:30 AM
Altavia Altavia is offline
Sage
Join Date: Jun 2019
Posts: 4,452
Thanks: 1,894
Thanked 3,418 Times in 1,628 Posts
Default

They've made a lot of progress, much of the approach ramps and the connection over the pipeline is in place.

Relative to what I saw for the Chitty Chatty bridge, I would not be surprised if it opened Feb/March. Others may have a better idea.
  #3  
Old 12-24-2020, 12:59 PM
photo1902 photo1902 is offline
Sage
Join Date: Nov 2014
Posts: 3,218
Thanks: 1,607
Thanked 1,745 Times in 706 Posts
Default

Quote:
Originally Posted by kpd3062 View Post
I have been gone for the last month and a half. I just read about Brownwood bridge and Meggison road opening. Have any of you been by Water Lily recently? Thanks
This is a view of the bridge from the north side of the turnpike, taken earlier today. A lot of progress being made on the ramp. More progress on the ramp has been done on the south side.
Attached Thumbnails
The Villages Florida: Click image for larger version

Name:	North side.jpg
Views:	3399
Size:	121.2 KB
ID:	87472  
  #4  
Old 12-25-2020, 10:33 AM
kpd3062's Avatar
kpd3062 kpd3062 is offline
Senior Member
Join Date: Aug 2017
Location: Texas
Posts: 123
Thanks: 410
Thanked 39 Times in 21 Posts
Default Picture

Thanks for the picture
  #5  
Old 12-25-2020, 01:17 PM
JoMar JoMar is offline
Sage
Join Date: Apr 2014
Posts: 4,973
Thanks: 10
Thanked 2,479 Times in 938 Posts
Default

Now that the Brownwood Bridge (and Meggison) is open you can drive and watch the progress. Wide open spaces now but give it a few months, it is a fun ride.
__________________
No one believes the truth when the lie is more interesting

Berks County Pennsylvania
  #6  
Old 12-25-2020, 05:48 PM
FG111 FG111 is offline
Senior Member
Join Date: Jul 2020
Posts: 103
Thanks: 8
Thanked 220 Times in 53 Posts
Default

I'm very close to the second cousin of the bag boy who works at The Publix located on SR44, who spent his winter break with the foreman in charge of the final construction phase of the bridge who advised him that the projected completion date of the Water Lily bridge is currently Friday, February 5th, 2021, subject to change.......
  #7  
Old 12-26-2020, 06:51 AM
cleser cleser is offline
Junior Member
Join Date: Feb 2020
Posts: 12
Thanks: 2
Thanked 22 Times in 9 Posts
Default

You are so full of it! His cousins sister, heard they moved it to March 10th.
I’ll believe it - when I see it!
  #8  
Old 12-26-2020, 06:55 AM
Minoletti Minoletti is offline
Member
Join Date: Mar 2019
Location: Marsh Bend
Posts: 67
Thanks: 5
Thanked 88 Times in 35 Posts
Default

Did the bag boy ever marry that cashier Eunice?
__________________
Ron
  #9  
Old 12-26-2020, 08:50 AM
Homer49 Homer49 is offline
Senior Member
Join Date: Oct 2019
Location: Village of Marsh Bend
Posts: 110
Thanks: 106
Thanked 92 Times in 48 Posts
Default

Here's a shot from the south side taken Christmas morning. They've now set the precast spans that bridge the gas pipeline in place, so it looks like all the heavy lifting is done. Ramp work making good progress as well.

(may need to click to expand)
img_1009-png
  #10  
Old 12-26-2020, 11:29 AM
benj benj is offline
Senior Member
Join Date: Jun 2008
Posts: 343
Thanks: 2
Thanked 21 Times in 12 Posts
Default Water Lilly bridge

Quote:
Originally Posted by FG111 View Post
I'm very close to the second cousin of the bag boy who works at The Publix located on SR44, who spent his winter break with the foreman in charge of the final construction phase of the bridge who advised him that the projected completion date of the Water Lily bridge is currently Friday, February 5th, 2021, subject to change.......
Man I thought a new Cosco was coming there for a second.
__________________
Champaign,IL Ypsilanti,Dearborn Heights,MI Firestone,CO Now Duval.
My can do can’t keep up with my want to.
  #11  
Old 12-28-2020, 08:38 AM
rwfisher1969's Avatar
rwfisher1969 rwfisher1969 is offline
Member
Join Date: Mar 2018
Location: Village of Winifred
Posts: 91
Thanks: 826
Thanked 33 Times in 23 Posts
Default



Quote:
Originally Posted by FG111 View Post
I'm very close to the second cousin of the bag boy who works at The Publix located on SR44, who spent his winter break with the foreman in charge of the final construction phase of the bridge who advised him that the projected completion date of the Water Lily bridge is currently Friday, February 5th, 2021, subject to change.......
  #12  
Old 12-28-2020, 08:41 AM
rwfisher1969's Avatar
rwfisher1969 rwfisher1969 is offline
Member
Join Date: Mar 2018
Location: Village of Winifred
Posts: 91
Thanks: 826
Thanked 33 Times in 23 Posts
Default

No, that opens February 6th! Trader Joe's on the 7th!


Quote:
Originally Posted by benj View Post
Man I thought a new Cosco was coming there for a second.
  #13  
Old 12-28-2020, 09:13 AM
C4Boston C4Boston is offline
Senior Member
Join Date: Oct 2017
Location: Fenney
Posts: 112
Thanks: 56
Thanked 92 Times in 36 Posts
Default

just waiting for the toll booth to be put in place.
  #14  
Old 12-28-2020, 07:34 PM
M2inOR M2inOR is offline
Senior Member
Join Date: Mar 2019
Location: Village of Marsh Bend
Posts: 382
Thanks: 240
Thanked 256 Times in 160 Posts
Default

Quote:
Originally Posted by benj View Post
Man I thought a new Cosco was coming there for a second.
I was hoping it would be a Costco... 😉
__________________
--------------------------------------------
Mike
Village of Marsh Bend
--------------------------------------------
We live in interesting times
--------------------------------------------