They were there yesterday working on the road. I think few issues in play when they work on it or on hold for a reason.
  #17  
Old 10-27-2022, 07:03 AM
retiredguy123 retiredguy123 is offline
Sage
Join Date: Feb 2016
Posts: 14,434
Thanks: 2,378
Thanked 13,860 Times in 5,307 Posts
Default

Quote:
Originally Posted by Stu from NYC View Post
I am sure Lynette spent lots of time looking into this before wasting everyone time with a pathetic answer
I asked her for an update today, so she is probably busy working on it.
  #18  
Old 10-27-2022, 08:08 AM
maistocars maistocars is offline
Senior Member
Join Date: Sep 2021
Posts: 337
Thanks: 302
Thanked 185 Times in 112 Posts
Default

The Villages would have completed that boondoggle within 2 weeks.
__________________
"He who dares not offend cannot be honest." Thomas Paine
  #19  
Old 10-27-2022, 08:48 AM
Stu from NYC Stu from NYC is online now
Sage
Join Date: Feb 2020
Posts: 12,844
Thanks: 1,173
Thanked 14,222 Times in 5,422 Posts
Default

Quote:
Originally Posted by retiredguy123 View Post
I asked her for an update today, so she is probably busy working on it.
Hope it does not interfere with her mid morning nap.
  #20  
Old 10-27-2022, 09:16 AM
wbilbrey99@yahoo.com wbilbrey99@yahoo.com is offline
Junior Member
Join Date: Jun 2021
Posts: 8
Thanks: 0
Thanked 5 Times in 3 Posts
Default

Winter, you want winter go to Chicago or New York this should have been done already.
  #21  
Old 10-27-2022, 11:29 AM
retiredguy123 retiredguy123 is offline
Sage
Join Date: Feb 2016
Posts: 14,434
Thanks: 2,378
Thanked 13,860 Times in 5,307 Posts
Default

Quote:
Originally Posted by retiredguy123 View Post
I asked her for an update today, so she is probably busy working on it.
Here is the update she sent to me today.

"Currently active work for this job includes paving operations and storm drainage installations within the project limits.
The project limits are from Lake Ella Road to Avenida Central; I drove by the site a couple days ago and witnessed paving operations being done.
This project is estimated to be completed Fall of 2023.

For the latest project updates visit: 238395-5 U.S. 441 Widening from Lake Ella Road to Avenida Central (cflroads.com)

Kind regards,

Lynette Cruz | Community Outreach Coordinator
EXP U.S Services
In-House FDOT Consultant, District 5
Ocala/Leesburg Construction
Office: 352-326-7744 / 352-620-3020
Cell: 352-359-7059
Lynette.Cruz@dot.state.fl.us
www.cflroads.com"
  #22  
Old 10-27-2022, 12:30 PM
CPD050 CPD050 is offline
Member
Join Date: May 2022
Posts: 37
Thanks: 10
Thanked 54 Times in 25 Posts
Default

Quote:
Originally Posted by nn0wheremann View Post
Supposedly the bride over Route 25 is the hang up. A worker died in a construction accident shortly after they started. More recently a sinkhole swallowed one or more of the bridge supports. Maybe it is haunted or cursed, this is the Deep South, doncha know.

Still, no excuse for not getting the rest of the work done. Those Bozos would never get away with the delay in Chicago for sure.
Chicago is horrible for construction projects. Always late for completion, sometimes by years, always over budget because certain people have to get their cut of the project. Then they use inferior quality material so it has to be redone well before it’s life expectancy. But at least the politicians get their kick back
  #23  
Old 10-27-2022, 03:36 PM
DaleDivine DaleDivine is offline
Platinum member
Join Date: Apr 2014
Posts: 1,679
Thanks: 516
Thanked 876 Times in 532 Posts
Wink

Quote:
Originally Posted by retiredguy123 View Post
Here is the update she sent to me today.

"Currently active work for this job includes paving operations and storm drainage installations within the project limits.
The project limits are from Lake Ella Road to Avenida Central; I drove by the site a couple days ago and witnessed paving operations being done.
This project is estimated to be completed Fall of 2023.

For the latest project updates visit: 238395-5 U.S. 441 Widening from Lake Ella Road to Avenida Central (cflroads.com)

Kind regards,

Lynette Cruz | Community Outreach Coordinator
EXP U.S Services
In-House FDOT Consultant, District 5
Ocala/Leesburg Construction
Office: 352-326-7744 / 352-620-3020
Cell: 352-359-7059
Lynette.Cruz@dot.state.fl.us
www.cflroads.com"
There you go... An updated answer.
  #24  
Old 10-27-2022, 04:41 PM
Worldseries27 Worldseries27 is offline
Platinum member
Join Date: Oct 2019
Posts: 1,539
Thanks: 351
Thanked 890 Times in 504 Posts
Default

Quote:
Originally Posted by nn0wheremann View Post
supposedly the bride over route 25 is the hang up. A worker died in a construction accident shortly after they started. More recently a sinkhole swallowed one or more of the bridge supports. Maybe it is haunted or cursed, this is the deep south, doncha know.

Still, no excuse for not getting the rest of the work done. Those bozos would never get away with the delay in chicago for sure.
i say contract it out to the egyptians. They know how to build on sand
  #25  
Old 10-27-2022, 06:01 PM
Worldseries27 Worldseries27 is offline
Platinum member
Join Date: Oct 2019
Posts: 1,539
Thanks: 351
Thanked 890 Times in 504 Posts
Default

Quote:
Originally Posted by wbilbrey99@yahoo.com View Post
winter, you want winter go to chicago or new york this should have been done already.
chicago wins hands down with the hawk and lake michigan blizzards
  #26  
Old 10-27-2022, 06:45 PM
Stu from NYC Stu from NYC is online now
Sage
Join Date: Feb 2020
Posts: 12,844
Thanks: 1,173
Thanked 14,222 Times in 5,422 Posts
Default

Quote:
Originally Posted by retiredguy123 View Post
Here is the update she sent to me today.

"Currently active work for this job includes paving operations and storm drainage installations within the project limits.
The project limits are from Lake Ella Road to Avenida Central; I drove by the site a couple days ago and witnessed paving operations being done.
This project is estimated to be completed Fall of 2023.

For the latest project updates visit: 238395-5 U.S. 441 Widening from Lake Ella Road to Avenida Central (cflroads.com)

Kind regards,

Lynette Cruz | Community Outreach Coordinator
EXP U.S Services
In-House FDOT Consultant, District 5
Ocala/Leesburg Construction
Office: 352-326-7744 / 352-620-3020
Cell: 352-359-7059
Lynette.Cruz@dot.state.fl.us
www.cflroads.com"
Wonder if they get paid by the day and that is why it takes so long
Closed Thread

Tags
highway, halted, construction, explain, year